The Plan856 views
|
|

Six Years Later739 viewsRepainted, windows replaced with aluminium and garden re-landscaped.
|
|

Bathroom575 viewsBoth bathrooms are tiled floor to ceiling for ease of cleaning. Also the bathrooms are 'dry', i.e. the shower at the end remote from the door behind a protective wall.
|
|

Wall paper and furnishings in the lounge563 views
|
|

Accommodation542 viewsAccommodation for the night watchman/cement storage shed
|
|

The Green Field Site541 views1 Rai (1,600 sq.m.) of land raised and ready for building.
|
|

The Kitchen540 viewsTiled from floor to ceiling to facilitate cleaning. The kitchen units are installed on a 100 mm high concrete plinth to increase the height of the work surfaces.
|
|

Column Footing Excavation534 views1.00 m x 1.00 m excavations down to solid.
|
|

Setting Out512 viewsThe sight rails
|
|

Ceremony487 viewsA ceremony is required before building proper could commence
|
|

The Bar Bending "Machine"481 viewsConsisting of a railway sleeper with strategically positioned re-bar cut offs
|
|

Concreting the Column Foundations468 viewsColumns - 6 No 12 mm rebar tied at 200 mm centres with 6 mm bar.
|
|

Septic Tank Design466 viewsSeptic tank for sewerage discharge.
|
|

Virtually Complete466 viewsJust a lick of paint on the gutters and downpipes required.
|
|

Internal Doors459 viewsIt was decided, contrary to Thai tradition, to install wooden doors to the bathrooms.
|
|

The Foreman458 views
|
|